Colorado Says 22 NEVI Charging Plazas Await Contracts; 18 Are Open

A November 18 commission briefing separates 64 NEVI projects into three stages and says a federal Fully Built-Out request is still being prepared.

This report reflects information available at publication or its last update; circumstances may have changed since then.

More Charging & Grid coverage →

Colorado told its Transportation Commission on November 18 that 22 NEVI-funded charging plazas had been awarded but were not yet contracted. Another 24 were actively being developed, and 18 were open. Those three agency-reported stages add up to 64 plazas, but only 18 were in the open category in that dated snapshot.1

The figures appear in slide 15 of the Colorado Department of Transportation's November 18–19 commission meeting packet. They clarify a distinction largely invisible in a headline about charging-project awards: a funded location may still be waiting for a contract rather than moving toward construction.1

Colorado's reported NEVI project stages

Stage in CDOT's November 18 briefing Plazas Share of the three-stage total*
Open since 2025 18 28.1%
Actively being developed 24 37.5%
Awarded but not yet contracted 22 34.4%
Total 64 100%

*Percentages are At The Charger's arithmetic from CDOT's three figures (18 + 24 + 22). The 22 awarded-but-uncontracted projects account for 22/64, or 34.4%, of this listed pipeline; the two categories not labeled open account for 46/64, or 71.9%. These are administrative plaza/project stages—not counts of charging connectors, broken equipment, or all public fast-charging stations in Colorado.1

Fully obligated does not mean fully open—or federally certified

The same briefing says Colorado's NEVI funding is fully obligated. Yet it separately identifies the 22 awarded-but-uncontracted plazas, and says the state was preparing its request for Federal Highway Administration Fully Built-Out status. Those statements describe different milestones: funding obligation, project contracting, operating charging locations, and a federal corridor-status determination. The briefing does not establish that every plaza has a signed agreement or that FHWA has granted the requested status.1

CDOT listed December 5, 2026 as the deadline for Round 10 applications. It said it hoped to award remaining NEVI funding by mid-2027, with project management potentially running through 2029 or 2030. Those are the department's plans and forecasts as presented November 18, not guaranteed opening dates for individual sites.1

Why August and September counts cannot simply be added

CDOT's August 27 update reported 17 NEVI locations open and 33 awarded and under development. The earlier At The Charger account of those dated figures explains why awarded sites should not be mistaken for working stations.2

August's two-stage, 50-location snapshot and November's three-stage, 64-plaza briefing do not provide a matched project-by-project ledger. The difference cannot establish that precisely 14 projects were newly awarded, or that an identifiable additional charging station opened. Project cohorts and status definitions may have changed between reports.12

Colorado also announced a September 22 funding cohort of 35 locations and 270 planned charging ports using a mix of federal NEVI and state Community Access Enterprise money. That mixed-funding announcement cannot be added wholesale to either NEVI-only snapshot. The projects were announced as planned additions, not an inventory of live ports.3

The November commission figures provide a clearer picture of administrative progress, but not an address-by-address operating directory. Determining which plazas have energized chargers, what connectors are available, or whether particular sites are reliable requires current site-level evidence the briefing does not supply.1

Sources

Footnotes

  1. Colorado Department of Transportation, Colorado Transportation Commission November 18–19, 2026 meeting packet, EV Charging Update, especially slides 14, 15 and 20. https://www.codot.gov/about/transportation-commission/documents-and-resolutions/commission-materials/2026-supporting-documents/november-2026-meeting-materials/november-2026-tc-packet-reduced-size.pdf — Primary official briefing for the November three-stage classification, funding-obligation statement, anticipated FHWA request and forward-looking dates. Percentages are ATC arithmetic, not official percentages. The oversized original PDF's text was inspected, but a separate visual slide rendering was not completed; this is not an independent site-level audit. ↩ ↩2 ↩3 ↩4 ↩5 ↩6 ↩7

  2. Colorado Department of Transportation, “Colorado nears a fully built-out statewide electric vehicle fast-charging network,” August 27, 2026. https://www.codot.gov/news/2026/august2026news/colorado-nears-statewide-ev-fast-charging-network — Primary prior-vintage 17-open/33-awarded-under-development NEVI counts. Different date and classification from November; cannot reconcile individual site changes. ↩ ↩2

  3. Colorado Energy Office / Colorado Department of Transportation, “Polis Administration Awards $23.2 Million to Fill Gaps in Colorado's Electric Vehicle Fast-Charging Network,” announcement September 22, 2026, issuer-originated full text republished by Global Renewable News. https://www.globalrenewablenews.com/article/energy/category/energy-storage/84/1219752/polis-administration-awards-23-2-million-to-fill-gaps-in-colorado-s-electric-vehicle-fast-charging-network.html — Establishes announced 35 locations and 270 prospective ports with mixed NEVI/Community Access Enterprise funding. The original state-hosted award spreadsheet and unmixed site list were not independently authenticated. ↩