Alpitronic Plans $34M South Carolina Factory—but Its Chargers Were Already Made in Wisconsin

The February 2027 Fort Mill target is about bringing HYC400 and HYC1000 production under Alpitronic's direct control, not introducing American-made Alpitronic chargers for the first time.

This report reflects information available at publication or its last update; circumstances may have changed since then.

More Batteries & Supply Chain coverage →

Alpitronic plans to spend $33.94 million on a South Carolina factory for its HYC400 and HYC1000 fast chargers, with operations expected in February 2027. But this is not the start of American-made Alpitronic hardware. In a June 13, 2024 announcement, Mercedes-Benz High-Power Charging said the HYC400 units it planned to deploy were already being produced at a Wisconsin facility.12

The distinction is who Alpitronic intends to put in charge of its future U.S. production. In the South Carolina Department of Commerce's November 18, 2026 announcement, Alpitronic Americas CEO Patrik Herrnegger described the Fort Mill project as bringing American manufacturing under the company's direct control. That is an announced intention—not evidence that the plant has opened, or that Wisconsin production stopped or changed hands.12

What changed—and what was already here

Date U.S. operation described in the original record What that record establishes
May 2023 Charlotte, North Carolina headquarters and technology, test and repair center City-announced regional headquarters project; not proof that charger manufacturing began there3
June 2024 Wisconsin-produced HYC400 chargers for Mercedes-Benz High-Power Charging Mercedes said equipment intended for its U.S. network was produced domestically; the release did not identify the factory's legal owner2
November 2026 Fort Mill, South Carolina manufacturing, testing and repair site A newly announced project, intended to make HYC400/HYC1000 hardware with February 2027 expected initial operations—not completed production1

The June 2024 Mercedes release is the important historical check: it explicitly identified Wisconsin, not just a vague commitment to American sourcing. WFAE's September 2024 reporting, carried by Blue Ridge Public Radio, likewise described Alpitronic hardware manufacturing in Wisconsin and Italy. Neither source establishes who legally operated the Wisconsin facility, whether it still operates today or whether production will move to South Carolina. Describing the Fort Mill project as the company's first-ever U.S. charger manufacturing would therefore conflate the new facility with a manufacturing activity already reported two years earlier.24

What the Fort Mill site is meant to do

South Carolina lists 3560 Stateview Blvd. as the address of a planned 173,315-square-foot operation covering Hypercharger production, a testing lab, repairs, warehousing, logistics and offices. The state and company anticipate 70 new jobs. Those figures describe plans and targets; they are not audited investment, employment or factory-output totals. The state separately reported job-development credits and a $200,000 grant to York County for building improvements, not a consumer charging discount.1

The product distinction also matters. Alpitronic describes the HYC1000 as a distributed charger with up to 1 megawatt from a power cabinet, dynamically shared by as many as eight simultaneously charging vehicles. It does not promise 1 MW for each connected car. The manufacturer's specification describes hardware capability; the new South Carolina announcement does not prove the factory has built, certified, shipped or installed a single HYC1000.15

For charging-network operators, the concrete new development is Alpitronic's plan for a company-controlled U.S. production and service site that could support its hardware supply. The reviewed records do not establish future delivery volumes, better uptime, faster repairs, Buy America certification, or cheaper charging for drivers. Those outcomes require actual commissioning, customer shipments and operating evidence—not the announcement of a factory alone.125

Sources

Footnotes

  1. South Carolina Department of Commerce, "Alpitronic Americas selects York County for first South Carolina operation," November 18, 2026. Original agency announcement quoting Alpitronic Americas CEO; investment, jobs, address, intended site functions, direct-control rationale and expected start are plans. https://www.sccommerce.com/newsroom/alpitronic-americas-selects-york-county-first-south-carolina-operation ↩ ↩2 ↩3 ↩4 ↩5 ↩6

  2. Mercedes-Benz High-Power Charging, "Deploying Made-in-America Alpitronic Hardware," original issuer release, June 13, 2024. States HYC400 equipment planned for its network was already produced at a Wisconsin facility; does not identify that facility's legal operator or current status. https://www.prnewswire.com/news-releases/mercedes-benz-high-power-charging-accelerates-investment-in-the-us-clean-energy--transportation-economy-deploying-made-in-america-alpitronic-hardware-302171893.html ↩ ↩2 ↩3 ↩4 ↩5

  3. City of Charlotte, "alpitronic Americas Chooses Charlotte for US Headquarters," May 23, 2023. Original municipal announcement of Charlotte headquarters and test/repair center. https://www.charlottenc.gov/CS-Prep/City-News/alpitronic-Americas-Chooses-Charlotte-for-US-Headquarters ↩

  4. WFAE original local reporting, carried by Blue Ridge Public Radio, "EV charger manufacturer Alpitronic opens its American headquarters in Charlotte, North Carolina," September 19, 2024. Named outlet's account of Wisconsin and Italy manufacturing; separately attributed, not direct plant ownership evidence. https://www.bpr.org/2024-09-19/ev-charger-manufacturer-alpitronic-opens-its-u-s-headquarters-in-charlotte ↩

  5. Alpitronic U.S., "Hypercharger HYC1000" product specifications, accessed November 18, 2026. Up to 1 MW shared cabinet architecture; up to eight simultaneous vehicles; not proof of Fort Mill production, installed customer equipment or charging speeds per vehicle. https://www.alpitronic.it/us/hypercharger/hyc-1000/ ↩ ↩2