California Approves $5.24M in NEVI Grants for 39 Planned Fast-Charging Ports

Final November 18 CEC orders approve AmpAway and Lightning Grown grants for six proposed charging sites; the exact addresses are known but construction and opening dates remain unverified.

This report reflects information available at publication or its last update; circumstances may have changed since then.

More Charging & Grid coverage →

Update — November 19, 2026: The CEC's newly docketed final orders confirm that the agency approved AmpAway resolution 26-1118-08a and Lightning Grown resolution 26-1118-08b on November 18, with four AYE votes, zero NAY votes and one commissioner absent. Those decisions replace the original draft resolutions' unknown vote status, but they do not establish signed agreements, paid grants or operating chargers.1

The California Energy Commission approved two grants on November 18, 2026, for plans to build 39 public CCS fast-charging ports at six locations. The approved CEC grants total $5,237,790 for AmpAway and Lightning Grown, while the original proposals specify $1,309,449 in planned private matching funds. The approval is established in final CEC orders; the figures are not grants shown to have been paid or chargers shown to be operating.1234

The Commission's short presentation lists the six cities and rounds the proposed funding. The longer underlying agreement scopes specify the actual street addresses, making it possible to check the intended locations and port counts together.234

The six proposed charging sites

Proposed recipient Proposed address New CCS fast-charging ports
AmpAway 15018 Clark Ave, Hacienda Heights, CA 91745 14
AmpAway 25211 Sunnymead Blvd, Moreno Valley, CA 92553 8
Lightning Grown 3144 Del Monte Blvd, Marina, CA 93933 4
Lightning Grown 2933 US-50, South Lake Tahoe, CA 96150 4
Lightning Grown 2370 Main St, Red Bluff, CA 96080 4
Lightning Grown 2036 Forest Ave, Chico, CA 95928 5
Total 6 proposed locations 39

At The Charger crosswalk of the two original CEC proposed scope-of-work site tables: AmpAway RNEV-26-002, page 12 of its scope; Lightning Grown RNEV-26-003, page 11 of its scope. These are proposed project sites, not a list of active charging stops.34

Lightning Grown's agreement calls for 640 kW of total new CCS charger power at each of Marina, South Lake Tahoe and Red Bluff, and 800 kW at Chico. Both proposed agreements call for at least four 150-kW-or-higher CCS ports at each station, capable of simultaneously charging four vehicles at 150 kW. These are design requirements, not measured station capabilities. AmpAway's site table labels both of its power entries “150 kW” without clearly stating whether that figure means each port or the entire site, so it cannot support a total-site-power calculation.34

How the proposed funding compares

Approved grant agreement Approved NEVI grant Planned private match Planned ports Approved grant per planned port
AmpAway — RNEV-26-002 $1,661,190 $415,299 22 ~$75,509
Lightning Grown — RNEV-26-003 $3,576,600 $894,150 17 ~$210,388
Combined $5,237,790 $1,309,449 39 ~$134,302

Grant approvals are confirmed in the CEC's final orders; the private-match numbers come from the staff presentation. Per-port figures divide the approved grant by proposed port counts. These are grant-budget ratios, not actual equipment costs, paid amounts or evidence of operating-site efficiency.1234

The combined approved grants and planned private match represent $6,547,239 in stated project funding. That is not the same as California having spent $6.55 million, nor does it mean the state is providing the private-match portion.234

Are the grants approved, or the chargers open?

Both grants were approved on November 18, 2026. The chargers are not shown to be open. Final CEC resolutions, released through the public docket November 19, explicitly approve $1,661,190 for AmpAway and $3,576,600 for Lightning Grown LLC. The resolutions authorize the commission's executive director or designee to execute the project agreements, but are not themselves proof of a completed contract, an actual grant payment or the beginning of installation.1

The original draft forms contained placeholder resolution numbers and blank vote fields when first reviewed on November 18. That earlier observation was accurate for the then-available proposal documents, but is superseded by the adopted orders. The six addresses, 39 port counts, stated nameplate capabilities and matching funds remain project plans—not confirmed working equipment, consumer prices or commissioning dates.341

The proposed agreements also state further work conditions involving federal highway authorization and a written CEC notice to proceed. No evidence reviewed here establishes those later milestones or individual charger availability.341

The six-site comparison also covers only two Item 8 agreements from November 18's meeting. CEC staff separately describes the broader GFO-25-602 solicitation as encompassing 11 proposed awards, 343 ports and 58 locations, associated with approximately $79 million for fast-charging deployment. The solicitation's notice of proposed awards predates the November 18 meeting, with a revised public notice dated November 16; November 18 was not the initial announcement of this program's proposed selections.25

Drivers should verify actual station availability through the relevant live charging network before planning a stop. The documents examined here establish what the applicants propose to build, not an operational route or a commissioning schedule.

Sources

Footnotes

  1. California Energy Commission, Orders and Resolutions of the November 18, 2026 Business Meeting, Item 8, adopted November 18 and filed November 19, 2026 (Docket 26-BUSMTG-01, TN 273723). Signed final resolutions 26-1118-08a and 26-1118-08b establish approved grant amounts and recorded votes, not signed contracts, payments, completed chargers or operation. https://efiling.energy.ca.gov/GetDocument.aspx?DocumentContentId=121542&tn=273723 ↩ ↩2 ↩3 ↩4 ↩5 ↩6

  2. California Energy Commission, November 18, 2026 business-meeting Item 8 presentation — agency-originated proposed-agreement summary, city-level port counts, private matching amounts, program-wide figures and staff recommendation. https://www.energy.ca.gov/filebrowser/download/10061?fid=10061 ↩ ↩2 ↩3 ↩4 ↩5

  3. California Energy Commission, AmpAway, proposed RNEV-26-002 agreement and scope of work, November 18, 2026 meeting backup packet — proposed resolution and grant, page 12 of scope (PDF page 20) exact proposed addresses/ports and federal/work-authorization conditions. Resolution is a proposed blank-vote form, not a verified adopted decision. https://www.energy.ca.gov/filebrowser/download/10058?fid=10058 ↩ ↩2 ↩3 ↩4 ↩5 ↩6 ↩7 ↩8

  4. California Energy Commission, Lightning Grown LLC, proposed RNEV-26-003 agreement and scope of work, November 18, 2026 meeting backup packet — proposed resolution and grant, page 11 of scope (PDF page 19) four addresses/ports and stated proposed site power. Resolution is a proposed blank-vote form, not a verified adopted decision. https://www.energy.ca.gov/filebrowser/download/10059?fid=10059 ↩ ↩2 ↩3 ↩4 ↩5 ↩6 ↩7 ↩8

  5. California Energy Commission, GFO-25-602 program solicitation and revised proposed-award index — solicitation published December 29, 2025; November 16, 2026 revised notice of proposed awards. Program status metadata does not itself establish adoption of the November 18 Item 8 resolutions. https://www.energy.ca.gov/solicitations/2025-12/gfo-25-602-californias-national-electric-vehicle-infrastructure-formula ↩