New Jersey's Board of Public Utilities signed its PowerUp New Jersey order on November 12, establishing a framework for utility-run virtual power plants. The important distinction for electric-car owners is that managed EV charging can fit the interim demand-response program, but the order does not itself authorize an owner to enroll a particular car or charger, and compensation for exporting power from an EV battery is reserved for consideration under a later, long-term VPP framework.1
The signed order also puts today's EV contribution in perspective. In its inventory of 437 megawatts of previously subsidized, controllable demand-response device capacity, just 15 MW came from EV chargers. That is 15 ÷ 437 = 3.43%, an At The Charger calculation from the regulator's historical categories—not the share of New Jersey EVs enrolled in PowerUp, power delivered by cars or capacity already operating under the new program.1
Three different technologies, three different answers
| Technology or activity | What the November 12 order establishes | What it does not establish |
|---|---|---|
| Managed EV charging — reducing or shifting the time a car draws electricity | EV chargers can be considered under a technology-neutral framework for dispatchable load reduction, subject to each utility's proposed and approved program | A list of eligible vehicles, chargers or software, an open signup, or an owner payment amount |
| Vehicle-to-grid (V2G) export — sending energy from an EV battery back to the grid | The Board adopted a recommendation to address compensation in a later, long-term VPP framework | An approved V2G export payment or vehicle-specific export permission under this order |
| Stationary behind-the-meter battery storage | A separate Block 1 storage program includes performance-incentive maximums of up to $200/kW per year for new systems and $100/kW per year for existing systems, subject to program terms | Those rates as an EV-charger rebate or a payment for energy exported from a car |
The distinctions above come from the order's operative requirements and accompanying EV-related material. They should not be treated as a determination that an individual installation qualifies.1
The distinction matters because turning down charging load is not the same service as discharging a vehicle battery. New Jersey's interim approach allows utilities to propose the former without promising that any bidirectional car, home charger or interconnection will be approved for the latter.1
What happens next for the four utilities
PSE&G, Jersey Central Power & Light, Atlantic City Electric and Rockland Electric must submit their interim VPP program proposals to the Board by February 12, 2027. Subject to Board approval of those filings, the programs must be operational by October 1, 2027. The approved interim program term extends through September 30, 2029. The October date is a utility-program deadline, not a verified date when any particular EV owner can begin earning money.1
The adopted framework generally limits dispatch events to three hours each and 35 events per calendar year, unless a utility justifies a different limit and the Board approves it. Compensation to qualifying VPP host customers must take the form of money rather than a utility-bill credit. Those rules describe the proposed operating structure; they do not specify which EV drivers qualify or what they would be paid.1
To make a real enrollment decision, an owner will still need an approved utility offering that identifies compatible equipment, eligible customer classes, control and opt-out conditions, actual payment terms and an enrollment process. The November order requires later utility filings rather than supplying those answers today.1
How much of the earlier flexible-load inventory was EV charging?
The Board's historical inventory lists 420 MW of smart thermostats, 15 MW of EV charging and 2 MW of water heaters, totaling 437 MW of previously subsidized controllable device capacity. EV charging therefore accounts for approximately 3.43% of that specific prior inventory; thermostats account for most of it. The calculation describes an existing program resource mix, not PowerUp's future installed capacity, vehicle count or actual grid-dispatch performance.1
New Jersey Monitor reporter Nikita Biryukov first reported the Board's November 12 approval. The subsequently accessible signed Board order provides the controlling text for the distinctions between EV charging, V2G export and stationary storage incentives explained here.21
Sources
Footnotes
-
New Jersey Board of Public Utilities — Order Establishing PowerUp NJ and Adopting Minimum Filing Requirements, signed and effective November 12, 2026, including Attachments A–H. Official signed order (PDF). Relevant printed pages include 1–2, 7, 20, 49–55 and Attachments A/C. This final statewide order does not substitute for later individual electric utility program approvals, enrollment rules or tariff terms. ↩ ↩2 ↩3 ↩4 ↩5 ↩6 ↩7 ↩8 ↩9
-