WattEV's Oakland Truck Charging Plan Now Lists Seven 1.2-MW Positions, Up From Six

The opening announcement implies an 8.4-MW theoretical charging mode, but earlier project records and PG&E's flexible connection explain why that is not a guaranteed site power figure.

This report reflects information available at publication or its last update; circumstances may have changed since then.

More Charging & Grid coverage →

WattEV announced the opening of its eighth California electric-truck charging depot on November 23, 2026, at the Port of Oakland. Comparing that announcement with the company's June 2025 groundbreaking release reveals a change: the proposed high-power mode now accommodates seven trucks at 1.2 MW each rather than six. That raises its theoretical combined charging output from 7.2 MW to 8.4 MW, but does not establish that the site has that much power available from the grid.12

What changed in the Oakland charging design

Both company announcements identify the project at 8407 Edgewater Drive. The lower-power charging option remains unchanged. Multiplying the stated per-truck ratings by the respective simultaneous truck counts produces the following comparison.12

Announced configuration June 24, 2025 November 23, 2026
Lower-power mode 25 × 240 kW = 6 MW 25 × 240 kW = 6 MW
Megawatt mode 6 × 1.2 MW = 7.2 MW 7 × 1.2 MW = 8.4 MW

The megawatt-mode difference is 1.2 MW, or approximately 16.7% relative to the earlier design. These are alternative configurations, not capacity totals to add together. The figures are calculated from published specifications rather than measured charging performance; the releases do not establish the reason for the revision.12

The Bay Area Air District described the project differently in its April 21, 2026, announcement: 36 chargers with a combined 7.2 MW, and expected availability to fleets by March 25, 2027. That earlier description is not an as-built inventory or a current utility service limit. November's opening announcement does not independently establish that the April fleet-availability expectation has been met.31

Why the electrical connection matters

WattEV identifies PG&E's Flex Connect program as Oakland's power arrangement. PG&E explains that the service can connect controllable loads ahead of grid upgrades and provides customers with advance forecasts of hourly power limits.14

WattEV's separate Fresno depot illustrates the distinction. Its June 30, 2026, opening release describes approximately 1 MW of firm grid capacity there. PG&E's Central Valley regional vice president, Josh Simes, said the flexible arrangement could support up to 3.6 MW during most hours. The release identifies a longer-term capacity upgrade planned for mid-2028. Those figures apply to Fresno, not Oakland.5

Oakland access still needs confirmation

As checked November 23, WattEV's location index still categorizes Oakland as under development. The listing could lag the opening announcement; it does not establish that the facility is closed. The sources reviewed do not establish Oakland's current access hours, commissioned connector availability, or firm and flexible grid limits. Fleet planners should confirm those operational details before scheduling trucks around the advertised charging modes.614

Sources

Footnotes

  1. Oakland depot opening announcement — WattEV, November 23, 2026, via GlobeNewswire. https://www.globenewswire.com/news-release/2026/11/23/3408557/0/en/wattev-s-port-of-oakland-charging-depot-and-new-electric-trucks-bring-cost-parity-with-diesel-to-fleets.html — Operator's opening announcement, stated charging modes and Flex Connect arrangement; not an independent operational test. ↩ ↩2 ↩3 ↩4 ↩5 ↩6

  2. Oakland depot groundbreaking announcement — WattEV, June 24, 2025, via GlobeNewswire. https://www.globenewswire.com/news-release/2025/06/24/3104427/0/en/WattEV-breaks-ground-at-Port-of-Oakland-on-its-sixth-heavy-duty-electric-truck-charging-depot-in-CA.html — Historical design at the same address, used with S001 for arithmetic. ↩ ↩2 ↩3

  3. East Oakland electric-truck charging project financing — Bay Area Air District, April 21, 2026. https://www.baaqmd.gov/News-and-Events/Page-Resources/2026-News/042126-WattEV — Earlier project description and anticipated fleet availability. ↩

  4. Flex Connect service announcement — PG&E, April 28, 2025. https://investor.pgecorp.com/news-events/press-releases/press-release-details/2025/New-PGE-Service-Offering-Makes-It-Easier-and-Faster-to-Connect-EV-Chargers-EV-Fleets-and-Big-Batteries-to-the-Grid/ — General program mechanics, not Oakland-specific grid limits. ↩ ↩2

  5. Fresno depot opening announcement — WattEV, June 30, 2026, via GlobeNewswire. https://www.globenewswire.com/news-release/2026/06/30/3319857/0/en/WattEV-opens-heavy-duty-electric-truck-charging-depot-in-Fresno-CA.html — Fresno-specific flexible and firm power information, including a named PG&E representative's statement. ↩

  6. Depot location index — WattEV, undated, checked November 23, 2026. https://wattev.wattsystems.com/locations — Dated observation of the Oakland listing, not proof of actual access or closure. ↩