EV Realty announced on November 17 that construction had begun on its electric-truck charging hub in Torrance, California. But the 50-stall, 9-megawatt project has a different configuration from the one previously proposed: California project records show a reduction from 60 to 50 planned charging stalls while proposed simultaneous EV charging capacity increased from 7.6 MW to 9 MW.12
That is 10 fewer planned stalls (16.7%) but 1.4 MW more planned simultaneous charging power (18.4%). The changes were documented in a March 18, 2026 Caltrans project-programming request, not adopted or newly announced on groundbreaking day. The comparison comes from the original state project documents rather than the November construction press release.23
What changed in the Torrance plan
| Project detail | Earlier public plan | Revised/current plan |
|---|---|---|
| Charging stalls | 60 planned | 50 planned |
| Advertised individual stall ratings | Up to 300 kW pull-in and 500 kW pull-through | 30 up to 350 kW; 20 up to 1,200 kW |
| Planned simultaneous EV charging capacity | 7.6 MW, identified as the prior level in the March 2026 request | 9.0 MW |
| Expected opening | 2026 in the older project fact sheet | Mid-2027, according to EV Realty's November 17 announcement |
The earlier stall layout and opening projection came from an EV Realty/Caltrans project fact sheet. The newer ratings appear in the March 2026 state project material and EV Realty's current Torrance page. All entries describe plans or projections, not installed, operating charging equipment.3241
The March filing attributes the redesign to the larger footprint needed for Megawatt Charging System (MCS) equipment, Southern California Edison equipment-access and clearance requirements, and maneuvering room for Class 8 trucks. EV Realty's project submission says the planned utility/equipment yard needed approximately 15% more area. These are the applicant's documented design explanations, not independently tested equipment performance.2
Why 50 high-power stalls do not mean 34.5 MW at once
EV Realty's current project page describes 30 planned stalls rated up to 350 kW and 20 rated up to 1,200 kW. Adding the individual maximum ratings yields 30 × 350 + 20 × 1,200 = 34,500 kW, or 34.5 MW. But the Caltrans project request identifies 9,000 kW of simultaneous EV charging capacity for the facility.42
Those figures have different meanings: 34.5 MW is only the sum of separate per-stall advertised maxima, not the site's promised concurrent output. The checked documents do not establish a particular power-allocation algorithm, actual session speeds, or the number of trucks that could simultaneously receive their maximum advertised stall rating. A fleet operator should not use the 34.5-MW sum as an available-power commitment.42
EV Realty says the proposed site will accommodate both CCS and MCS charging. Its location page still marks the property under development, and the company projects commercial service in mid-2027. The page outlines dedicated-stall rental with energy-cost pass-through and an on-route per-kWh pricing format, but, as reviewed November 17, it does not give a numeric public charging rate. No operating charging sessions, installed hardware inventory or specific truck compatibility were independently verified.14
The actual milestone on November 17 is EV Realty's announcement that work has begun at 18715 S. Western Avenue. The older government filings explain how the planned charging layout evolved before that announcement; they do not by themselves verify construction progress or guarantee the scheduled opening.12
Sources
Footnotes
-
EV Realty, “EV Realty Breaks Ground on 9 MW Truck Charging Hub in Torrance,” November 17, 2026, original company press release via GlobeNewswire. Supports company-announced construction commencement, site location, proposed CCS/MCS support and projected mid-2027 commercial opening; construction was not independently observed. https://www.globenewswire.com/news-release/2026/11/17/3404536/0/en/ev-realty-breaks-ground-on-9-mw-truck-charging-hub-in-torrance.html ↩ ↩2 ↩3 ↩4
-
California Transportation Commission / Caltrans, “EV Realty South Bay Truck Charging Hub Project Baseline Agreement,” including March 18, 2026 Project Programming Request v6, original state-hosted project plan. Its project-amendment section records 60-to-50 stalls, 7,600-to-9,000 kW simultaneous EV charging capacity, MCS redesign and applicant-described yard/turning constraints. These are proposed project figures, not measured site output. The source's large-PDF text was checked; visual rendering of the exact amendment page timed out. https://catc.ca.gov/-/media/ctc-media/documents/programs/baseline-agreements/2026-05/ev-realty-south-bay-ba.pdf ↩ ↩2 ↩3 ↩4 ↩5 ↩6 ↩7
-
EV Realty / Caltrans, “EV Realty South Bay Truck Charging Hub,” older 2024-program project fact sheet, original publicly posted project concept, visually reviewed November 17, 2026. Lists 60 proposed stalls with up-to-300-kW pull-in and up-to-500-kW pull-through equipment and a superseded 2026 operational target. This is historical, not the current construction configuration. https://catc.ca.gov/-/media/ctc-media/documents/programs/tcep/2024/receipt-log-fact-sheets/19-ev-realty-south-bay-truck-charging-hub-project-fact-sheet-a11y.pdf ↩ ↩2
-
EV Realty, “Torrance, CA” operator project page, reviewed November 17, 2026. Lists under-development status, 30 proposed stalls up to 350 kW and 20 up to 1,200 kW, 9 MW of grid power, and commercial pricing formats without numeric rates. Mutable interested-party page, not operational test data. https://evrealtyus.com/projects/torrance-ca/ ↩ ↩2 ↩3 ↩4